Sr. No. | Description of Works | Client | Start | End |
---|---|---|---|---|
1 | Al Aballah School rehabilitation | Save The Children Organization | 2004 | 2004 |
2 | Construction of a laboratory for Medicine Collage | UN | 2006 | 2006 |
3 | Construction of Al-Ferzdaq Secondary School In Al Qurna | UN | 2006 | 2006 |
4 | Rehabilitation of the roofing of Arts Collage | Government Of Basrah | 2006 | 2006 |
5 | Construction of Civil Engineering department building in Bab Al Zubair | SOC | 2006 | 2007 |
6 | Construction of Dormitories | Thi-Qar University | 2007 | 2007 |
7 | Construct of AL_Hurria Diesel Power Plant 62MW ( Wartsila10x6.2 MW). | Ministry of Industry | 2007 | 2007 |
8 | Al Furat River stone laying | Water resources directorate | 2008 | 2008 |
9 | Al Habanya Base projects | Areebel | 2009 | 2009 |
10 | Construction of Service & administrative Buildings for new Maysan refinery | Maysan refinery | 2009 | 2009 |
11 | Construction of MCC Building for AL_ Qudes Power | State company for industrial design | 2009 | 2009 |
12 | Tunnel excavation for the sport city feeding pipe | Youth Ministry | 2011 | 2011 |
13 | Al Fyhaa bridge rehabilitation | Road and bridges directorate of Basrah | 2011 | 2012 |
14 | Construction of concrete cooling towers with different capacities at the South Refineries Co. site | State Company for Industrial Design | 2011 | 2012 |
15 | Supply concrete for SRC projects | South Refineries Company | 2013 | 2013 |
16 | Construction of water treatment Unit with capacity of ( 2000m3/day ) at the SRC | State Company for Industrial Design | 2013 | 2014 |
17 | Implementation of Water Treatment plant 10,000m3/h for Basra Sport City | Ministry of Sports | 2013 | 2014 |
18 | Supplying and install 4 units of water treatment for Hay Al Hussain Water project in Basrah, capacity of each unit is 400 m3/h | Basra Water directorate | 2016 | 2016 |
19 | Supplying and install 4 unit of water treatment for Shat Al Arab Water project in Basrah, each unit capacity is 400 m3/h | Basra Water directorate | 2015 | 2016 |
20 | Design and construction of Square shoot for 10th battalion in Nasryah | Corps of Engineers | 2015 | 2016 |
21 | Rehabilitation of al garage pump station and construction the Administration buildings, Service buildings and generator room ,Site works, Civil works for sewage collecting tank and Warehouse shed | Basra sewer directorate | 2015 | 2016 |
22 | Supply material, equipment and labors to construct a complete packaged sewage treatment plant and standby generator suitable for a population equivalent of 50,000 people as in the design drawings and the specification | Basra sewer directorate | 2015 | 2016 |
23 | Design and construction of Al-Sabla canal of lining and the work is including, excavation, dewatering and pouring concrete | Ministry of Water Resource | 2016 | 2017 |
24 | The installation of 11KV, 22 KV and 33KV, substations. Our services also include CT, PT & LA, Isolators, gantries and towers | JCCI/Babil | 2016 | 2017 |
25 | Construction of Emergency building in Azubair Hospital in Basrah Governorate (2000m2) with 2 stories, this project including Excavation and filling, and concrete works for fundation, columes, slabs, … ( more than 2000m3 reinforced concrete) | Basrah support rebuild and services committee | 2016 | 2017 |
26 | Equipment's Installation of Liquefied Petroleum Gas Unit/ at the South Refineries Co | South Refineries Company | 2017 | 2017 |
27 | Rehabilitation of Khalid Bridge at Basra city (consist of support, pilling, Lifting | Ministry of Housing & Construction | 2017 | 2017 |
28 | Supply and installation of 730 concrete pile | General Company for South Oil Refineries | 2017 | 2017 |
29 | Implementation of the earthworks for the Fluidized Catalytic Cracking project (4 million m3 ) at the site of south refineries | State Company for Industrial Design | 2016 | 2017 |
30 | Steel Structure for AL-Shabah printing house | Ministry of Industry | 2016 | 2017 |
31 | Rehabilitation of ALBUFRAJ Bridge | Directorate of Roads and Bridges | 2016 | 2017 |
32 | Fluidized Catalytic Cracking-FCC (Extensional Adjacent Area) | State Company for Industrial Design | 2016 | 2017 |
33 | Installation of Mechanical, Electrical and Instrument works such 1. Static Equipment Installation 2. Rotary Equipment Installation 3. Piping Installation 4. Valves Installation 5. Supports 6. NDT 7. Hydro-Test 8. Sand Blast 9. Painting 10. Flushing 11. Pre commissioning 12. Cable Installation 13. LV Transformer 14. ML Transformer 15. Electrical Equipment Installation 16. Electronic Equipment Installation 17. Power Panels 18. Power Generator Installation |
Petrofac International (UAE) LLC . | 2017 | 2018 |
34 | Providing all the requirement and manpower to provide 125m3 + 175 m3 of Fire Protection Concrete | Sajer | 2017 | 2018 |
35 | First Commercial and Production (FCP) Garraf Oil and Gas project in Southern Iraq. The project includes the EPC of storage tanks and the construction of piping systems, process units, LP & ATM. The current FCP Garraf project is designed for 100kbpd oil from the Mishrif formation utilizing two (2) oil processing trains of 50 kbpd capacity each. | Lakeshore Toltest Corporation | 2017 | 2018 |
36 | Design and Engineering, Procurement, Construction and commissioning of Basrah Crude Distillation No.4 Unit, LPG Unit and Boiler | TECHNO EXPORT | 2018 | 2018 |
37 | Installation of prefabricated steel structural buildings for LCR ,LER ,Gurd House and four guard towers each one consist of three stories. The project is located in WQ1, the work includes but not limited steel structure installation, electrical work, cable try installation, HVAQ system installation, G&F system. | EMIL | 2018 | 2019 |
38 | Installation of prefabricated steel structural building for LCR ,The project is located in WQ1, the work includes but not limited steel structure installation, electrical work, cable try installation, HVAQ system installation, G&F system | EMIL | 2018 | 2019 |
39 | Providing various required Scaffolding along with required skilled manpower, Scaffolding materials. The scope will start from mobilization/demobilization of skilled & experienced manpower, required scaffolding materials, equipments, tools & tackles to COMPANY site for erecting or dismantling of Scaffolding as per COMPANY Scaffolding procedures and permit requirements and the types of scaffolding is including but not limited to the following : 1. Supply and install Tube and Coupler cantilever scaffolding type. 2. Supply and Install Tube and Coupler suspendable scaffolding Type. 3. Supply and install Tube and Coupler mobile Scaffolding type. 4. Supply and install Tube and Coupler Tower scaffolds type. |
Bp Iraq N.V | 2018 | 2019 |
40 | Installation of Mechanical, Electrical and Instrument works such as vessels, pumps, electrical panels, .. Etc. | STX/SOC | 2018 | 2019 |
41 | Installation of Piping and Pipeline | ZFOD | 2017 | 2020 |
42 | Mechanical,Electrical,Insrtrumentationa and Piping works at Badra Oil Field | Petrofac | 2017 | 2020 |
43 | Provisions of competent, experienced and a professional manpower and equipment/vehicle as further described in this scope of service to support: • Pre commissioning • Commissioning • Maintenance • Shutdown activities • Scaffolding Services |
Petrofac International (UAE) LLC | 2018 | 2020 |
Sr. No. | Description of Works | Client | Start | End |
---|---|---|---|---|
1 | Water pipe installation to Al Mayahe Street in Abu Al Khaseeb | Save The Children Organization | 2004 | 2004 |
2 | Pipeline installation (28 in) from Sweeb station to Majnoon oil field | SOC | 2006 | 2007 |
3 | Construction of Service & administrative Buildings for new Maysan refinery | Maysan refinery | 2009 | 2009 |
4 | Installation of Hydrogenation unit pressure plants at South Refinery Co.site | State Company for Industrial Design | 2011 | 2012 |
5 | Construct of Baiji GasTurbine power plant 6x160MW sgt5-pack2000E siemense | Ministry of Electricity | 2012 | 2012 |
6 | Rehabilitation of pumps, motors, generators, power and control cables, and electrical panels | Water directorate-Basra | 2013 | 2014 |
7 | Design and construction of water pipe line at Al-Meshraq Area | Mott MacDonald | 2013 | 2014 |
8 | Paving and repair of Al Tamimiyah Road ,including excavation, filling, grading, compacting, leveling and paving with asphalt, of 10Km length. The works includes concrete works for intersections of 25cm depth and total 1400 m3. | Ministry of Municipalities and Public Works | 2013 | 2014 |
9 | Construction of water treatment Unit with capacity of ( 2000m3/day ) at the SRC | State Company for Industrial Design | 2013 | 2014 |
10 | Implementation of Water Treatment plant 10,000m3/h for Basra Sport City | Ministry of Sports | 2013 | 2014 |
11 | Excavation Laying of pipeline (1000 mm. Dia.x18KM.L) from pump station to Water Water pipe feeding (900 mm) Dia, 18 km length for Basra Sport city | Ministry of Sports | 2013 | 2014 |
12 | Ductile Pipeline,22 Km length in AL-Nasiriya Industrial City | Ministry of Industry | 2013 | 2014 |
13 | Supply material, equipment and labors to Excavation, supplying and Laying sewer network piping and manholes for Hay Al Hussain | Basra sewer directorate | 2015 | 2015 |
14 | Supply and install difference size of pipes, Replace unsuitable materials, Reinstatement and other works for successfully finishing project | Basra Water directorate | 2015 | 2015 |
15 | Design and construction of a pump system with piping for KHOR AL ZUBYAR harbor. | Iraqi tankers co. | 2015 | 2015 |
16 | Fabrication, welding and laying pipe line and pipe fittings at Majnon Oilfield – Basra - Iraq | Shell - Iraq | 2015 | 2015 |
17 | Supply material, equipment and labors to supplying and install (INLET CHAMBER , TRASH SCREEN, LIFTING CRANES, SUBMERSIBLE PUMPS, PIPING AND FITTINGS ) , including all necessary buildings and fences. | Basra sewer directorate | 2015 | 2015 |
18 | Install the water pipes network containing supply and install difference size of pipes, Replace unsuitable materials and other works for successfully finishing project | Basra Water directorate | 2014 | 2015 |
19 | Supplying and install 4 units of water treatment for Hay Al Hussain Water project in Basrah , capacity of each unit is 400 m3/h | Basra Water directorate | 2016 | 2016 |
20 | Maintenance and Widening Bradhyaa Water Project including supply and install different sizes of pipes, maintenance all water pumps, filters, valves and other works for project success | Basra Water directorate | 2015 | 2016 |
21 | Supplying and install 4 unit of water treatment for Shat Al Arab Water project in Basrah , each unit capacity is 400 m3/h | Basra Water directorate | 2015 | 2016 |
22 | Rehabilitation of al garage pump station and construction the Administration buildings, Service buildings and generator room, Site works, Civil works for sewage collecting tank and Warehouse shed | Basra sewer directorate | 2015 | 2016 |
23 | Supply material, equipment and labors to construct a complete packaged sewage treatment plant and standby generator suitable for a population equivalent of 50,000 people as in the design drawings and the specification | Basra sewer directorate | 2015 | 2016 |
24 | Piping Process networks for AL-Shaiba Refinery including : sandblasting , welding , NDE ,PWHT Thermal Insulation, cladding and coating | South Refineries | 2015 | 2016 |
25 | Line Polyethylene water pipeline network in the 14 Tamoze street size 500 mm and 450 mm | Basra Water directorate | 2016 | 2017 |
26 | Fabrication, welding and laying pipe line with installing manifold and pipe fittings at Majnon Oilfield | Shell - Iraq | 2016 | 2017 |
27 | The installation of 11KV, 22 KV and 33KV, substations. Our services also include CT, PT & LA, Isolators, gantries and towers | JCCI/Babil | 2016 | 2017 |
28 | Equipment's Installation of Liquefied Petroleum Gas Unit/ at South Refineries Co | South Refineries Company | 2017 | 2017 |
29 | Hydro test and Pneumatic test at Badra CPF | Petrofac | 2018 | 2018 |
30 | Installation of Mechanical, Electrical and Instrument works such 1. Static Equipment Installation 2. Rotary Equipment Installation 3. Piping Installation 4. Valves Installation 5. Supports 6. NDT 7. Hydro-Test 8. Sand Blast 9. Painting 10. Flushing 11. Pre commissioning 12. Cable Installation 13. LV Transformer 14. ML Transformer 15. Electrical Equipment Installation 16. Electronic Equipment Installation 17. Power Panels 18. Power Generator Installation |
Petrofac International (UAE) LLC . | 2017 | 2018 |
31 | Fabrication, welding and installing flow line and piping system will all pipe fittings at Hamar Mushrif gas compressor station Basra - Iraq | ENI | 2017 | 2018 |
32 | First Commercial and Production (FCP) Garraf Oil and Gas project in Southern Iraq. The project includes the EPC of storage tanks and the construction of piping systems, process units, LP & ATM. The current FCP Garraf project is designed for 100kbpd oil from the Mishrif formation utilizing two (2) oil processing trains of 50 kbpd capacity each. | Lakeshore Toltest Corporation | 2017 | 2018 |
33 | The project is EPCC of the export pipeline for Garraf Contract Area to export the crude oil from the FCP at Garraf to Ahdep Pipeline which exports the crude oil further to the government depot at Nasseryah city.The project consists of 8km of 18" pipeline with the related facilities such as fiber optic, leak detection system, launching and recieving stations, 2 block valve stations and the required tie-ins. | Petronas Caligari Iraq Holding B.V. | 2017 | 2018 |
34 | Scope of Work in KAZ area as follow: • Installation and hook-up of gas treatment facility. • Erection of ME&I equipment and structures • Tie-ins in gas treatment facility existing • Interconnecting to gas treatment facility • Installation of power and control cables. • Installation of piping system with all insulation works |
KBR | 2017 | 2018 |
35 | Complete of the external evaluation of the crude oil export pipeline in Bazargan – ALFAO | State Company for Inspection &Engineering Rehabilitation ( SIER ) | 2017 | 2018 |
36 | Design and Engineering , Procurement , Construction and commissioning of Basrah Crude Distillation No.4 Unit , LPG Unit and Boiler | TECHNOEXPORT | 2018 | 2018 |
37 | Hvac Works For Control & Substation Buildings :Supply And Install Galvanzied Steel With Corosion Resistance Coating And Insect Screen, Galvanized Steel Frame, Blade & Accesoreis. Stainless Steel Frame, Blade & Accessories, Low Leakage Type, Amca Class Ii (Min.) | CCC/Shell | 2018 | 2019 |
38 | Installation of prefabricated steel structural buildings for LCR ,LER ,Gurd House and four guard towers each one consist of three stories. The project is located in WQ1, the work includes but not limited steel structure installation, electrical work, cable try installation, HVAQ system installation, G&F system. | EMIL | 2018 | 2019 |
39 | Heat Excahnger Rehablitation Service | Bp Iraq N.V | 2017 | 2019 |
40 | Installation of prefabricated steel structural building for LCR ,The project is located in WQ1, the work includes but not limited steel structure installation, electrical work, cable try installation, HVAQ system installation, G&F system | EMIL | 2018 | 2019 |
41 | Providing various required Scaffolding along with required skilled manpower, Scaffolding materials. The scope will start from mobilization/ demobilization of skilled & experienced manpower, required scaffolding materials, equipments, tools & tackles to COMPANY site for erecting or dismantling of Scaffolding as per COMPANY Scaffolding procedures and permit requirements and the types of scaffolding is including but not limited to the following: 1. Supply and install Tube and Coupler cantilever scaffolding type. 2. Supply and Install Tube and Coupler suspendable scaffolding Type. 3. Supply and install Tube and Coupler mobile Scaffolding type. 4. Supply and install Tube and Coupler Tower scaffolds type. |
Bp Iraq N.V | 2018 | 2019 |
42 | Installation of Mechanical, Electrical and Instrument works such as vessels, pumps, electrical panels, etc. | STX/SOC | 2018 | 2019 |
43 | Installation of Piping and Pipeline | ZFOD | 2017 | 2020 |
44 | Mechanical,Electrical,Insrtrumentationa and Piping works at Badra Oil Field | Petrofac | 2017 | 2020 |
45 | 1. Provisions of competent, experienced and a professional manpower and equipment/vehicle as further described in this scope of service to support: • Pre commissioning • Commissioning • Maintenance • Shutdown activities • Scaffolding Services |
Petrofac International (UAE) LLC . | 2018 | 2020 |
Sr. No. | Description of Works | Client | Start | End |
---|---|---|---|---|
1 | Installation of 132 kv GIS Substation At Washash Substation | Washington Group Co. | 2008 | 2008 |
2 | Construction of Service & administrative Buildings for new Maysan refinery | Maysan refinery | 2009 | 2009 |
3 | Construct of Baiji GasTurbine power plant 6x160MW sgt5-pack2000E siemense | Ministry of Electricity | 2012 | 2012 |
4 | Construction of water treatment Unit with capacity of ( 2000m3/day ) at the SRC | State Company for Industrial Design | 2013 | 2014 |
5 | Implementation of Water Treatment plant 10,000m3/h for Basra Sport City | Ministry of Sports | 2013 | 2014 |
6 | Supplying and install 4 units of water treatment for Hay Al Hussain Water project in Basrah, capacity of each unit is 400 m3/h | Basra Water directorate | 2016 | 2016 |
7 | Supplying and install 4 unit of water treatment for Shat Al Arab Water project in Basrah , each unit capacity is 400 m3/h | Basra Water directorate | 2015 | 2016 |
8 | Rehabilitation of al garage pump station and construction the Administration buildings, Service buildings and generator room, Site works, Civil works for sewage collecting tank and Warehouse shed | Basra sewer directorate | 2015 | 2016 |
9 | Supply material, equipment and labors to construct a complete packaged sewage treatment plant and standby generator suitable for a population equivalent of 50,000 people as in the design drawings and the specification | Basra sewer directorate | 2015 | 2016 |
10 | The installation of 11KV, 22 KV and 33KV, substations. Our services also include CT, PT & LA, Isolators, gantries and towers | JCCI/Babil | 2016 | 2017 |
11 | Installation of a new electrical network by: Supply & installation of an over head line 200 circular & 38 lattice steel poles. Supply & installation of 10 transformers (Capacity 250KVA) with accessories | Mott MacDonald | 2016 | 2017 |
12 | Equipment's Installation of Liquefied Petroleum Gas Unit/ at the South Refineries Co | South Refineries Company | 2017 | 2017 |
13 | Installation of Mechanical, Electrical and Instrument works such 1. Static Equipment Installation 2. Rotary Equipment Installation 3. Piping Installation 4. Valves Installation 5. Supports 6. NDT 7. Hydro-Test 8. Sand Blast 9. Painting 10. Flushing 11. Pre commissioning 12. Cable Installation 13. LV Transformer 14. ML Transformer 15. Electrical Equipment Installation 16. Electronic Equipment Installation 17. Power Panels 18. Power Generator Installation |
Petrofac International (UAE) LLC . | 2017 | 2018 |
14 | First Commercial and Production (FCP) Garraf Oil and Gas project in Southern Iraq. The project includes the EPC of storage tanks and the construction of piping systems, process units, LP & ATM. The current FCP Garraf project is designed for 100kbpd oil from the Mishrif formation utilizing two (2) oil processing trains of 50 kbpd capacity each. | Lakeshore Toltest Corporation | 2017 | 2018 |
15 | Design, Supply, Installation, Testing & Commissioning of Substation on Turnkey | GE | 2018 | 2018 |
16 | Design and Engineering, Procurement, Construction and commissioning of Basrah Crude Distillation No.4 Unit , LPG Unit and Boiler | TECHNOEXPORT | 2018 | 2018 |
17 | Electrical and Instrumentation Work (Cable laying, Cable tray & Cable support Installation, cable termination, Instrumentation Works) | CCC/Shell | 2018 | 2019 |
18 | Installation of prefabricated steel structural buildings for LCR ,LER ,Gurd House and four guard towers each one consist of three stories. The project is located in WQ1, the work includes but not limited steel structure installation, electrical work, cable try installation, HVAQ system installation, G&F system. | EMIL | 2018 | 2019 |
19 | Heat Excahnger Rehablitation Service | Bp Iraq N.V | 2017 | 2019 |
20 | Installation of prefabricated steel structural building for LCR ,The project is located in WQ1, the work includes but not limited steel structure installation, electrical work, cable try installation, HVAQ system installation, G&F system | EMIL | 2018 | 2019 |
21 | Providing various required Scaffolding along with required skilled manpower, Scaffolding materials. The scope will start from mobilization/ demobilization of skilled & experienced manpower, required scaffolding materials, equipments, tools & tackles to COMPANY site for erecting or dismantling of Scaffolding as per COMPANY Scaffolding procedures and permit requirements and the types of scaffolding is including but not limited to the following : 1. Supply and install Tube and Coupler cantilever scaffolding type. 2. Supply and Install Tube and Coupler suspendable scaffolding Type. 3. Supply and install Tube and Coupler mobile Scaffolding type. 4. Supply and install Tube and Coupler Tower scaffolds type. |
Bp Iraq N.V | 2018 | 2019 |
22 | Installation of Mechanical, Electrical and Instrument works such as vessels, pumps, electrical panels, etc. | STX/SOC | 2018 | 2019 |
23 | Electrical Infrastructure Installation | ExxonMobil | 2019 | 2020 |
24 | Installation of Piping and Pipeline | ZFOD | 2017 | 2020 |
25 | Mechanical, Electrical, Instrumentation and Piping works at Badra Oil Field | Petrofac | 2017 | 2020 |
26 | 1. Provisions of competent, experienced and a professional manpower and equipment/vehicle as further described in this scope of service to support: • Pre commissioning • Commissioning • Maintenance • Shutdown activities • Scaffolding Services |
Petrofac International (UAE) LLC . | 2018 | 2020 |